Which step comes first in the guy installation process?

Get more with Examzify Plus

Remove ads, unlock favorites, save progress, and access premium tools across devices.

FavoritesSave progressAd-free
From $9.99Learn more

Prepare for the International Rodeo Exam with interactive quizzes and detailed explanations. Evaluate your knowledge of rodeo rules and safety protocols. Achieve success with our comprehensive study materials!

In the guy installation process, the first step is to install the anchor. This is crucial because the anchor serves as the primary support point that will hold the guy wire in tension. Without securing the anchor first, the entire installation would be unstable and potentially unsafe. Once the anchor is firmly in place, it can then be connected to the guy wire, allowing for the appropriate tension to be established and ensuring that the structure is properly supported.

The other steps, such as fastening the guy to the pole, tightening the guy wire, and inserting the strain insulator, depend on the anchor being installed first, as the position and stability of the guy wire are determined by the anchor's location. Thus, starting with the anchor is foundational to the correct and safe installation of guy wires.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy